go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_NGET0087
Title Cable Installation Design & Innovation Project (CIDIP)
Status Completed
Energy Categories Other Power and Storage Technologies(Electricity transmission and distribution) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
National Grid Electricity Transmission
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 October 2013
End Date 01 January 2015
Duration 15 months
Total Grant Value £200,000
Industrial Sectors Power
Region London
Programme Network Innovation Allowance
 
Investigators Principal Investigator Project Contact , National Grid Electricity Transmission (100.000%)
Web Site http://www.smarternetworks.org/project/NIA_NGET0087
Objectives The objective of this project is to determine the design principles that would allows 400kV circuits with two cables per phase to match the ratings of a standard 400kV OHL. The project will be successful if National Grid have an increased learning in the area of uprating underground transmission routes. This could be successful delivery of each of the work packages detailed above, or highlighting what area is a cause for concern and identifying further work needed in that area.
Abstract National Grid have a need to underground transmission routes, based on consumer consultations and existing wayleaves. The problem that National Grid face is that undergrounding transmission routes is expensive and complex. A recent report commissioned by the IET, performed by Parsons Brinckerhoff, found that it may be possible to transmit the same amount of power through 2 cables per phase, as is transmitted through a standard OHL. National Grid need to conduct some work, as detailed below, to back up these findings. Research The method proposed is as follows: Potential Benefits from large conductor designs Ratings Improvement through installation Improved modelling techniques for Directional Drills Review of 105c short term operation Cost benefit analysis Summary report and industry workshopNote : Project Documents may be available via the ENA Smarter Networks Portal using the Website link above
Publications (none)
Final Report (none)
Added to Database 26/04/18